PEDC3# Jetty Conveyor System
Introduction
Location: Iloilo, Philippines
Client: P?yry Switzerland Ltd.
Scope of Work: Engineering, Supply
& Construction of Coal handling system starting from the jetty unloader to
the transfer tower outside the coal bunker.
Capacity of Power Plant: 150MW*1
Handling Material: Coal
BW of Conveyor: 1,200mm
Conveying Capacity: 900t/h